(optional HADAB Factory module, hidden until you switch it on):

  • Switch on: Settings → POS section → «Concrete, blocks and transport». A Concrete & transport screen appears under Production.
  • Daily board: «Today (dispatch)» tab → «Add a pour» (sales order and item, quantity, time) → pick the truck → Send: the delivery note is made and the trip opens.
  • Driver link: in Trucks, «Driver link» (QR or WhatsApp): the driver opens it on their phone and taps «Arrived», «Unloaded», «Back» — no sign-in, no GPS.
  • Cube tests: from Trips the cube icon logs a sample (due at 7 and 28 days); the Cube tests tab takes the strength (MPa), compares it with the item spec's target (e.g. C30) and prints a certificate.
  • Trucks: Trucks tab → add a truck (plate, type: mixer / tipper / flatbed / pump, capacity, default driver, odometer, service every N km).
  • Sites: Sites tab → a site (project) per customer; pick it on the sales order and the delivery address follows.
  • Mix: make the mix recipe in Manufacturing (cement, sand, aggregate per m³), then Mixes tab → switch Ready-mix on for the item. The quantity is then made at each delivery and its materials leave at real cost. For blocks leave it off and make them with a normal production order.
  • Delivering: sales order → «Deliver» → pick the truck (its driver follows), the driver's pay and the weighbridge weights (gross and tare give the net). A trip is opened with the delivery note; the invoice follows as usual with the transport line.
  • Truck back: Trips tab → «Truck back»: kilometres and the driver's pay (booked as an expense once).
  • Fuel & maintenance: Fuel & maintenance tab → add a truck cost; it is booked as an ordinary expense, and «Serviced» restarts the service counter.
  • Report: each truck's profit (transport charged − fuel and maintenance − driver pay), and quantities by customer and day.
  • Not there: a link to the batching plant, block machine or weighbridge device, GPS tracking, pump scheduling.
  • Cancelling a delivery note cancels its trip and takes the ready-mix made for it back out of stock. If that concrete was already sold or used, a warning says it stayed in stock, so adjust it by hand

Steps

  1. Switch the module on: Settings → POS section → «Concrete, blocks and transport». A «Concrete & transport» screen appears under Production.
  2. Add trucks in the Trucks tab (plate, type, capacity, driver, odometer, service every N km) and project sites in the Sites tab.
  3. Make the mix recipe in Manufacturing (cement, sand, aggregate per m³), then in the Mixes tab switch «Ready-mix» on and write the spec, for example C30.
  4. Create the sales order for the project, then in the «Today (dispatch)» tab add the pour (order, quantity, time), pick the truck and press «Send»: the delivery note is made, the trip opens, the quantity is made and its materials taken.
  5. Send the «Driver link» from the Trucks tab by WhatsApp or QR: the driver taps «Arrived», «Unloaded», «Back» on their phone — no sign-in, no GPS.
  6. In Trips press «Truck back» to enter the kilometres and the driver's pay, log fuel and maintenance in the Fuel & maintenance tab, and see each truck's profit in the Report tab.
  7. For concrete quality: in Trips tap the cube icon to log a sample, then at 7 and 28 days enter the strength in the Cube tests tab and print the certificate.

▶ Video tutorial: Concrete and transport: from the order to the trip and the truck report

If you get stuck on any step, ask the smart assistant inside the program.

Software page: Grocery & supermarket POS

Applies to these systems

Related lessons

HADAB course for supermarkets and shops · Learning center · Glossary

Questions about Concrete, blocks and transport: trucks, trips and cube tests

What is not included?

No direct link to the batching plant, block machine or weighbridge device (weights are typed in), no GPS tracking and no pump scheduling.

Does it suit a block factory?

Yes: the mix recipe, cost per block, sales orders for projects, delivery notes and the invoice. Leave «Ready-mix» off for blocks and make them with a normal production order.

How is ready-mix costed?

On Send a production order for the delivered quantity is made and finished at once, so the materials leave stock at real cost and the concrete comes in at that cost, then goes out on the delivery note.

Where are the driver's pay and fuel booked?

As ordinary expenses: fuel and driver pay in the delivery & shipping account, maintenance and tyres in the maintenance account.

How do I know a cube sample passed?

The 28-day strength is compared with the target taken from the item spec (for example C30 = 30 MPa) and shows «Pass» or «Fail».

هذه الصفحة بالعربي · یہ صفحہ اردو میں · Bu sayfa Türkçe · This page in Bangla

Ready to start?

Message us on WhatsApp and we will help you install and link with Fatoora.

+966 56 173 9500  ·  +966 50 062 6563

WhatsApp Free trial